The new Palomar Medical Center: A Look Ahead
The new Palomar Medical Center – Proposed Campus
(450 beds):
Hospital - 750,000 sq. ft.
-
168 Acuity Adaptable beds
-
192 Med/Surg beds
-
12 Operating Rooms
-
6 Cath. Labs. / Interventional
-
Radiology Rooms
-
48 E.D. Exam/Tx + 2 Trauma Rooms
-
17 Imaging Rooms
Three-month look ahead
-
Activities through 2007
-
Rock crushing, blasting of rock
-
Selection of concrete contractor
-
Detailing for foundations (reinforcing steel, rock anchors and anchor bolts)
-
Steel mill order
-
Complete hospital basement excavation
-
MEP systems fully coordinated in BIM model (Basement through Level 3)
Entire project look ahead
-
Major Milestones
-
Steel erection July 2008
-
MEP overhead rough-in December 2008
-
Drywall (non-priority) begins April 2009
-
Steel topping off July 2009
-
Tower roof complete March 2010
-
Tower weather-tight March 2010
-
Building energized March 2010
Elevators ready to use April 2010
-
Central plant ready to occupy Fall 2010
-
Hospital ready to occupy early 2012
Womens & Childrens Hospital –150,000 sq. ft.
(date of project and build to be determined)
-
20 LDR / Ante-Partum Rooms
-
44 Post-Partum Beds
-
16 Pediatric Beds
-
16 NICU Beds
-
3 Operating Rooms